The low bidder priced delineators, flexible post mounted, crossover, type i, yellow at a median $92.31 per each over the last 12 months (7 contracts), up 15% from the year before and up 54% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Sep 22, 2026 | Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate | 20 EA | $142 | $145 | 3 |
| Jun 5, 2026 | Mill & Overlay approximately 9 miles of US 84 Westbound Lanes from Collins to the Jones CoCovington | 92 EA | $130 | $152 | 3 |
| May 27, 2026 | Pavement Restoration of US 49 from the Hinds County Line to the Yazoo County Line, and ITSMadison, Hinds, Yazoo | 136 EA | $130 | $127 | 4 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 104 EA | $92.31 | $91.16 | 2 |
| Mar 24, 2026 | Mill & Overlay approximately 4.2 miles of US 84 from Bude to the Homochitto River BridgeFranklin | 28 EA | $77.72 | $77.62 | 3 |
| Mar 24, 2026 | Seal & Overlay approximately 12.1 miles of US 61 from the Tunica Agriculture Center to theTunica | 120 EA | $77.35 | $76.17 | 2 |
| Feb 24, 2026 | Mill & Overlay approximately 9.8 miles of SR 25 from Renfroe to the Attala County LineLeake | 100 EA | $85.00 | $85.00 | 5 |
| Aug 26, 2025 | Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe | 52 EA | $55.00 | $55.00 | 3 |
| Jun 24, 2025 | Seal & Overlay approximately 4.8 miles of US 82 from West Greensboro Street to West of HenMontgomery | 48 EA | $79.25 | $77.13 | 2 |
| May 28, 2025 | Overlay approximately 8 miles of US 84 from Chambers Road to Middle Fork CreekFranklin | 52 EA | $98.45 | $98.58 | 2 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 80 EA | $80.00 | $76.50 | 2 |
| Feb 25, 2025 | Mill & Overlay approximately 8 miles of US 98 from the end of the 5-Lane to the Bogue ChitPike | 48 EA | $85.85 | – | 1 |
| Dec 5, 2024 | Overlay approximately 6 miles of US 61 from Washington to the Jefferson County LineAdams | 40 EA | $85.00 | – | 1 |
| Nov 26, 2024 | Mill & Overlay approximately 5 miles of US 49 from the Forrest County Line to Richard KendCovington | 44 EA | $75.00 | $75.00 | 3 |
| Sep 25, 2024 | Overlay approximatelyCovington | 16 EA | $93.00 | $93.00 | 3 |
| Sep 25, 2024 | Overlay approximatelyKemper | 112 EA | $85.00 | $85.00 | 3 |
| Jul 30, 2024 | Pavement Restoration on approximately 11 miles of US 49 from 0.8 miles north of Old HighwaYazoo | 80 EA | $71.79 | $71.79 | 3 |
| Jul 23, 2024 | Scrub Seal & Overlay approximately 10 miles of US 61 from Clayton to State Aid RoadTunica | 68 EA | $70.00 | – | 1 |
| Jun 25, 2024 | Overlay approximatelyPontotoc | 4 EA | $60.00 | $60.00 | 4 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 12 EA | $100 | $104 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.