The low bidder priced type 3 object markers, om-3r or om-3l at a median $140 per each over the last 12 months (25 contracts), up 27% from the year before and up 87% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 8 EA | $316 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 4 EA | $163 | $163 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 36 EA | $288 | $125 | 4 |
| Sep 22, 2026 | Installation of Audible Thermoplastic Traffic Markings & Thermoplastic Pavement Markings oDeSoto, Panola, Tate | 185 EA | $150 | $193 | 2 |
| Sep 22, 2026 | Safety Improvements & Pavement Markings approximately 30.3 miles of MS 309 from Byhalia toMarshall | 83 EA | $150 | $175 | 2 |
| Sep 22, 2026 | Remove OGFC & Replace with Micro-Surface on I-55 for approximately 14.1 miles from approxiDeSoto, Tate | 22 EA | $131 | $134 | 3 |
| Sep 22, 2026 | Bridge Repair on US 45 over Norfolk Southern Railroad (Bridge Nos. 275.6A & 275.6B)Alcorn | 2 EA | $147 | $147 | 7 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 4 EA | $148 | $162 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 12 EA | $157 | $162 | 6 |
| Aug 25, 2026 | Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba | 4 EA | $150 | $150 | 4 |
| Aug 25, 2026 | Bridge Repair on SR 434 on Bridge No. 0.7 and Bridge Rehabilitation on SR 434 on Bridge NoSharkey | 8 EA | $150 | $150 | 3 |
| Aug 25, 2026 | SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee | 4 EA | $130 | $147 | 8 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 2 EA | $150 | $177 | 5 |
| Jun 30, 2026 | Thin Lift Overlay approximately 10.1 miles of MS 35 from 4 Forks to the Grenada County LinCarroll | 12 EA | $88.65 | $88.65 | 3 |
| Jun 23, 2026 | Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison | 35 EA | $140 | $145 | 2 |
| Jun 5, 2026 | Mill & Overlay approximately 10.1 miles of MS 178 from the Marshall County Line to the UniBenton | 146 EA | $75.00 | $75.00 | 3 |
| Jun 5, 2026 | Overlay approximately 14.3 miles of MS Highway 7 beginning at the Lafayette County Line goMarshall | 4 EA | $128 | – | 1 |
| May 27, 2026 | Widening of US 51 from Glenwild to North StreetGrenada | 28 EA | $110 | $115 | 2 |
| May 27, 2026 | Pavement Restoration of US 49 from the Hinds County Line to the Yazoo County Line, and ITSMadison, Hinds, Yazoo | 10 EA | $130 | $130 | 4 |
| Mar 24, 2026 | Scrub Seal approximately 18.7 miles of MS 330 from east of Front Street to the Calhoun CouYalobusha, Calhoun | 82 EA | $175 | $138 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.