The low bidder priced radar vehicle detection cable at a median $4.08 per linear foot over the last 12 months (2 contracts), up 9% from the year before and up 95% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 2.5K LF | $4.65 | $4.65 | 3 |
| May 27, 2026 | Widening of US 51 from Glenwild to North StreetGrenada | 3.5K LF | $3.50 | $3.88 | 2 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 6.6K LF | $4.00 | $4.00 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 4 miles of SR 302 from 0.25 mile west of Malone Road to 0.06 DeSoto | 12K LF | $3.75 | $3.77 | 2 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 19K LF | $3.75 | $4.05 | 3 |
| Jul 31, 2025 | Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc | 3.0K LF | $4.18 | $3.67 | 2 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles of US 98 from 400 feet west of Weathersby Drive to thLamar, Forrest | 4.7K LF | $2.45 | $2.73 | 2 |
| Jun 24, 2025 | Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson | 1.4K LF | $4.10 | $4.15 | 2 |
| May 28, 2025 | Mill & Overlay approximately 3 miles of SR 178 from North Access Road to Old SR 25Itawamba | 1.5K LF | $3.50 | $3.63 | 4 |
| Apr 30, 2025 | Scrub Seal & Micro-Surfacing approximately 1.6 miles of SR 305 from End No Access (Golf CoDeSoto | 5.1K LF | $3.85 | $4.03 | 2 |
| Apr 22, 2025 | Mill & Overlay approximately 1.3 miles of SR 7 from US 82 to Grenada Boulevard ExtendedLeflore | 1.3K LF | $3.50 | $3.50 | 3 |
| Apr 1, 2025 | Mill & Overlay approximately 4 miles of SR 15 from Queen Street to north of Audubon DriveJones | 5.9K LF | $4.00 | $4.20 | 3 |
| Mar 25, 2025 | Concrete Pavement Rehabilitation on approximately 2.3 miles of US 82 through IndianolaSunflower | 1.1K LF | $3.50 | $4.39 | 3 |
| Dec 5, 2024 | Mill & Overlay approximately 3 miles of US 51 from Nail Road to the Tennessee State LineDeSoto | 2.2K LF | $2.07 | $3.50 | 3 |
| Dec 5, 2024 | Mill & Overlay approximately 13 miles of SR 30 from the Lafayette County Line to Cherry BlUnion | 1.3K LF | $2.00 | $3.58 | 4 |
| Dec 5, 2024 | Mill & Overlay approximately 2 miles of SR 16 through the City of PhiladelphiaNeshoba | 4.2K LF | $5.23 | $5.23 | 5 |
| Nov 26, 2024 | Installation of Intelligent Transportation Systems on I-59 from 1.5 miles south of I-20, ILauderdale | 680 LF | $3.45 | $4.26 | 4 |
| Nov 26, 2024 | Intersection Improvements on US 49 at SR 35Covington | 1.1K LF | $3.90 | $3.60 | 3 |
| Sep 25, 2024 | Construction project, Pontotoc CountyPontotoc | 190 LF | $1.00 | – | 1 |
| Jul 11, 2024 | Construction project, Madison CountyMadison | 1.1K LF | $18.97 | $19.06 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.