The low bidder priced video vehicle detection cable at a median $1.50 per linear foot over the last 12 months (9 contracts), down 25% from the year before and down 43% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 65 LF | $5.05 | $5.05 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 636 LF | $3.25 | $3.25 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 8.5K LF | $0.50 | $0.63 | 6 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 1.2K LF | $1.90 | $1.90 | 3 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 5.1K LF | $1.80 | $1.80 | 3 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 200 LF | $1.00 | $1.25 | 5 |
| Jun 5, 2026 | Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo | 100 LF | $1.00 | – | 1 |
| May 27, 2026 | Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 mileLeake | 680 LF | $0.10 | $0.10 | 4 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 3.2K LF | $1.50 | $1.50 | 2 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles of US 98 from 400 feet west of Weathersby Drive to thLamar, Forrest | 1.6K LF | $6.85 | $6.92 | 2 |
| Apr 22, 2025 | Intersection Improvements on US 49 from Desoto Park Road to 500' south of East Wortham RoaHarrison | 192 LF | $1.00 | $2.00 | 2 |
| Apr 1, 2025 | Mill & Overlay approximately 4 miles of SR 15 from Queen Street to north of Audubon DriveJones | 2.4K LF | $1.00 | $1.20 | 3 |
| Feb 25, 2025 | Mill & Overlay approximately 9 miles of US 51 from the Madison City Limits to Dinkins StreMadison | 1.1K LF | $3.00 | $3.07 | 2 |
| Jun 11, 2024 | Construction project, Lafayette CountyLafayette | 420 LF | $1.25 | $2.80 | 5 |
| May 29, 2024 | Thin Lift Overlay on approximately 9 miles of SR 63 from Clara to SR 184 & approximately 2Wayne | 50 LF | $1.00 | $0.51 | 2 |
| May 29, 2024 | Traffic Signal Installation on US 49W at SRSunflower | 644 LF | $3.00 | $2.00 | 2 |
| Jan 24, 2024 | Construction project, Hinds CountyHinds | 12K LF | $2.50 | $3.08 | 2 |
| Jan 24, 2024 | Intersection Improvements at SRSmith | 60 LF | $60.00 | $59.00 | 5 |
| Jan 24, 2024 | Construction project, Harrison CountyHarrison | 1.2K LF | $1.16 | – | 1 |
| Dec 5, 2023 | Add 2 Lanes on US 49 from O'Neal Road to north of School Road, known as Federal Aid ProjecHarrison | 5.4K LF | $2.70 | $2.60 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.