The low bidder priced borrow excavation, ah, fme, class b9-6 at a median $19.00 per cubic yard over the last 12 months (11 contracts), down 37% from the year before and up 77% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 584K CY | $29.60 | $30.50 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 28K CY | $14.00 | $19.50 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 27K CY | $18.33 | – | 1 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 3.4K CY | $30.00 | – | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 3.4K CY | $24.95 | $25.92 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 137K CY | $15.50 | $16.15 | 6 |
| Feb 3, 2026 | Slide Repair on US 61 Southbound across from Fire Tower RoadAdams | 42K CY | $3.50 | $14.65 | 4 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 15K CY | $16.50 | $25.00 | 7 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 8.4K CY | $19.00 | $26.05 | 4 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 1.6K CY | $36.00 | $26.93 | 4 |
| Nov 20, 2025 | Emergency Slide Repair on MS 478 approximately 0.90 miles SE of Shivers RoadSimpson | 800 CY | $40.00 | $38.00 | 5 |
| Aug 26, 2025 | Copi Construction of Equipment Shed & Material Shed, and Lot Improvements in the Copiah CoCopiah | 29K CY | $19.50 | $22.34 | 4 |
| Jun 24, 2025 | Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson | 550 CY | $30.00 | $40.00 | 2 |
| Feb 25, 2025 | Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson | 19K CY | $25.00 | $25.00 | 5 |
| Jan 28, 2025 | Wayne Installation of Ramp Gates on I-59 from the Louisiana State Line to north of US 84 &Lincoln, Pike, Forrest, Jones, Lamar, Pearl River, Adams | 39 CY | $100 | $100 | 3 |
| Nov 26, 2024 | Installation of Intelligent Transportation Systems on I-59 from 1.5 miles south of I-20, ILauderdale | 315 CY | $84.30 | $138 | 4 |
| Oct 10, 2024 | Emergency Slide Repair on US 80 in ForestScott | 4.6K CY | $30.00 | $34.20 | 2 |
| Jul 30, 2024 | Pavement Restoration on approximately 11 miles of US 49 from 0.8 miles north of Old HighwaYazoo | 8.2K CY | $46.75 | $46.00 | 3 |
| Jul 11, 2024 | Construction project, Madison CountyMadison | 688K CY | $30.20 | $31.23 | 3 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 739K CY | $18.00 | $21.75 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.