The low bidder priced select material for undercuts, contractor furnished, fm at a median $145 per cubic yard over the last 12 months (16 contracts), up 2% from the year before and up 184% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 96 CY | $160 | $160 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 8 CY | $272 | $185 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 54 CY | $150 | $137 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 47 CY | $195 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 127 CY | $152 | $178 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 2.8K CY | $30.00 | – | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 740 CY | $97.85 | $130 | 3 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 34 CY | $132 | $186 | 3 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 26 CY | $100 | $75.00 | 6 |
| May 27, 2026 | Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers CJones | 2 CY | $304 | $253 | 2 |
| May 27, 2026 | Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison | 293 CY | $91.50 | $91.50 | 5 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 54 CY | $212 | $212 | 3 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 700 CY | $140 | $34.91 | 4 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 140 CY | $125 | $105 | 7 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 25 CY | $50.00 | $41.50 | 4 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 22 CY | $216 | $168 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 928 CY | $150 | $150 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 5 CY | $50.00 | $50.00 | 3 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 418 CY | $95.00 | $132 | 3 |
| Apr 1, 2025 | Mill & Overlay approximately 4 miles of SR 15 from Queen Street to north of Audubon DriveJones | 15 CY | $166 | $166 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.