The low bidder priced soil reinforcing mat at a median $3.92 per square yard over the last 12 months (8 contracts), up 21% from the year before and up 6% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 7.4K SY | $3.85 | $4.00 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 2.1K SY | $4.00 | $4.72 | 4 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 848 SY | $3.30 | $3.55 | 3 |
| Aug 25, 2026 | Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba | 111 SY | $10.00 | $5.63 | 4 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 201 SY | $8.00 | $8.71 | 6 |
| Apr 28, 2026 | Restricted Crossing U-Turn (RCUT) on US 278 at CR 217/405Lafayette | 387 SY | $3.00 | $3.00 | 5 |
| Feb 3, 2026 | Slide Repair on US 61 Southbound across from Fire Tower RoadAdams | 5.2K SY | $3.50 | $3.21 | 4 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 130 SY | $4.95 | $5.00 | 7 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 4.9K SY | $2.35 | $2.70 | 3 |
| Feb 25, 2025 | Bank Stabilization on SR 37 over Oakohay Creek (Bridge No. 4.3)Covington | 4.1K SY | $1.00 | $3.51 | 8 |
| Jan 28, 2025 | Bridge Replacement on SR 14 over Hashuqua Creek (Bridge No. 156.5)Noxubee | 401 SY | $3.00 | $3.55 | 5 |
| Jan 28, 2025 | Drainage Improvements on US 61 near BlakelyWarren | 5.5K SY | $5.24 | – | 1 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 928 SY | $21.50 | $3.00 | 3 |
| Nov 7, 2024 | Bridge Replacement on SR 12 over the Sunflower River (Bridge No. 23.9)Humphreys, Washington | 223 SY | $3.50 | $4.25 | 4 |
| Jun 4, 2024 | Bridge Replacements on USHolmes | 356 SY | $3.00 | $3.00 | 7 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 22K SY | $3.00 | $3.13 | 2 |
| Jan 31, 2024 | Bridge Replacements on SR 395 between SRWinston | 2.2K SY | $3.00 | $3.35 | 2 |
| Nov 2, 2023 | Bridge Replacements & Bank Stabilization on US 98 at the Pearl River (Bridge Nos. 118.5A &Marion | 144 SY | $3.40 | $3.20 | 2 |
| Oct 24, 2023 | Construction project, Jefferson CountyJefferson | 272 SY | $3.15 | $3.15 | 5 |
| Aug 22, 2023 | Intersection Improvements on USMadison | 201 SY | $5.00 | $5.70 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.