The low bidder priced scrub seal at a median $3.00 per square yard over the last 12 months (11 contracts), down 5% from the year before and up 34% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike | 69K SY | $3.33 | $4.00 | 3 |
| Jun 23, 2026 | Widen & Overlay approximately 2 miles of SR 26 from the east end of the Pearl River BridgePearl River | 155K SY | $3.75 | – | 1 |
| May 27, 2026 | Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the JuTishomingo | 169K SY | $3.50 | $3.50 | 2 |
| May 8, 2026 | Seal & Overlay approximately 16 miles of MS 501 from SR 18 to the Scott County LineSmith | 210K SY | $3.00 | $3.05 | 4 |
| May 8, 2026 | Scrub Seal and Overlay approximately 8 miles of SR 12 from Black Creek in Lexington to EllHolmes | 123K SY | $3.50 | $3.25 | 2 |
| Mar 24, 2026 | Scrub Seal approximately 18.7 miles of MS 330 from east of Front Street to the Calhoun CouYalobusha, Calhoun | 340K SY | $2.85 | $3.38 | 2 |
| Mar 24, 2026 | Seal & Overlay approximately 12.1 miles of US 61 from the Tunica Agriculture Center to theTunica | 381K SY | $2.75 | $2.73 | 2 |
| Feb 24, 2026 | Mill & Overlay approximately 3.4 miles of SR 854 from SR 39 to the Naval Air StationLauderdale | 113K SY | $2.70 | $2.75 | 3 |
| Feb 24, 2026 | Seal & Overlay approximately 8.5 miles of MS 44 from near Gates Road to the Lamar County LMarion | 120K SY | $3.15 | $3.20 | 3 |
| Feb 24, 2026 | Widen & Overlay approximately 10 miles of SR 149 from 0.3 Miles South of SR 14 to US 49WHumphreys | 133K SY | $2.80 | $2.80 | 2 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 326K SY | $2.30 | $2.30 | 4 |
| Sep 23, 2025 | Scrub Seal & Overlay approximately 6 miles of SR 27 from I-55 to the Hinds County LineCopiah | 88K SY | $3.15 | $3.00 | 4 |
| Aug 26, 2025 | Mill & Overlay approximately 9 miles of SR 346 from the beginning of State Maintenance to Pontotoc | 20K SY | $6.00 | $4.21 | 5 |
| Jun 24, 2025 | Seal & Overlay approximately 4.8 miles of US 82 from West Greensboro Street to West of HenMontgomery | 159K SY | $2.55 | $3.27 | 2 |
| Apr 30, 2025 | Scrub Seal & Micro-Surfacing approximately 1.6 miles of SR 305 from End No Access (Golf CoDeSoto | 53K SY | $5.50 | $5.25 | 2 |
| Feb 25, 2025 | Clarke Microsurface approximately 32 miles & Scrub Seal approximately 7 miles of various rJasper, Greene | 93K SY | $3.65 | $3.45 | 2 |
| Dec 5, 2024 | Seal & Overlay approximately 8 miles of SR 28 from the Strong River to SR 13Simpson | 117K SY | $2.80 | $2.70 | 2 |
| Nov 26, 2024 | Seal & Overlay approximately 8 miles of SR 4 from Galena Curve to SR 7Marshall | 124K SY | $2.80 | $2.89 | 3 |
| Jul 23, 2024 | Overlay approximately 12 miles of SR 43 from the Pearl River County Line to SRMarion | 23K SY | $3.25 | $3.63 | 2 |
| Jul 23, 2024 | Scrub Seal & Overlay approximately 10 miles of US 61 from Clayton to State Aid RoadTunica | 239K SY | $2.85 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.