The low bidder priced concrete for base repair at a median $225 per cubic yard over the last 12 months (10 contracts), down 19% from the year before and down 53% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Fog Seal approximately 6.2 miles of I-59 from 0.8 mile north of CR 39 to the Jasper/ClarkeJasper, Clarke | 15 CY | $200 | $226 | 2 |
| Oct 27, 2026 | Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River | 9 CY | $350 | – | 1 |
| Oct 27, 2026 | OGFC Lift on I-59 from US 45 to approximately 0.248 miles north of the Russell InterchangeLauderdale | 17 CY | $75.00 | – | 1 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 341 CY | $108 | $115 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 94 CY | $109 | $413 | 6 |
| Aug 25, 2026 | Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren | 19 CY | $400 | $484 | 3 |
| Jun 23, 2026 | Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison | 6 CY | $425 | $413 | 2 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 192 CY | $315 | $323 | 2 |
| Apr 28, 2026 | OGFC Lift approximately 5.3 miles on I-20 from MS 18 to US 80 (East Brandon)Rankin | 20 CY | $50.00 | $50.00 | 3 |
| Feb 24, 2026 | Overlay approximately 5.3 miles of SR 27 from 0.2 mile south of Old Highway 27 to 0.35 milCopiah | 25 CY | $250 | $250 | 5 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles of US 98 from 400 feet west of Weathersby Drive to thLamar, Forrest | 4 CY | $341 | $316 | 2 |
| Apr 30, 2025 | Mill & Overlay & Concrete Rehabilitation on approximately 2 miles of SR 25 from the BOSM tHinds | 20 CY | $105 | $105 | 3 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 75 CY | $200 | – | 1 |
| Mar 25, 2025 | Concrete Pavement Rehabilitation on approximately 2.3 miles of US 82 through IndianolaSunflower | 422 CY | $350 | $350 | 3 |
| Feb 25, 2025 | Remove & Replace approximately 13 miles of OGFC on I-20 from East Brandon to the Scott CouRankin | 15 CY | $277 | $277 | 3 |
| Oct 22, 2024 | Remove and Replace OGFC on approximately 20 miles of I-59 from North of Rocky Creek to theJones | 49 CY | $245 | – | 1 |
| Sep 25, 2024 | Overlay approximatelyKemper | 25 CY | $250 | $250 | 3 |
| Jul 30, 2024 | Pavement Restoration on approximately 11 miles of US 49 from 0.8 miles north of Old HighwaYazoo | 347 CY | $170 | $175 | 3 |
| Jun 25, 2024 | Intersection Improvements on USRankin | 3 CY | $350 | $385 | 2 |
| May 29, 2024 | Overlay approximatelyClarke | 7 CY | $175 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.