The low bidder priced 18" reinforced concrete pipe, class iii at a median $82.60 per linear foot over the last 12 months (13 contracts), down 11% from the year before and up 45% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$82.60
13 contracts
Median, prior 12 months
$92.50
20 contracts
Median, 2020
$56.81
7 contracts
Winner vs. field
5% below
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$40$60$80$100$1202020202120222023202420252026*$82.60
Price vs. quantityEvery winning price since 2020 (log scale)
$0$50$100$150$200101001.0K
Does quantity matter?Median winning price by quantity band
$0$20$40$60$80$100$86.00≤60$81.6060–256$80.00256–777$71.50>777

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Construction project, Madison CountyMadison1.0K LF$82.60$85.973
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren364 LF$100$1003
Oct 27, 2026Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin466 LF$85.00$85.784
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson72 LF$96.62–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin2.9K LF$71.50$81.056
Sep 22, 2026Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha16 LF$95.00–4
Sep 1, 2026Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie48 LF$48.00$82.206
Jul 28, 2026Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest40 LF$70.00$92.803
Jun 23, 2026Roundabout on US 51 at Green T RoadDeSoto712 LF$55.00$81.256
May 27, 2026Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin64 LF$75.00$82.752
Apr 28, 2026Restricted Crossing U-Turn (RCUT) on US 278 at CR 217/405Lafayette56 LF$97.42$97.425
Nov 25, 2025Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe104 LF$47.00$91.004
Nov 25, 2025Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington400 LF$101$84.804
Sep 23, 2025Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette4.8K LF$55.00$75.003
Sep 4, 2025Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln944 LF$82.50$82.503
Aug 26, 2025Copi Construction of Equipment Shed & Material Shed, and Lot Improvements in the Copiah CoCopiah60 LF$65.00$83.384
Aug 26, 2025Mill & Overlay approximately 9 miles of SR 346 from the beginning of State Maintenance to Pontotoc40 LF$135$2455
Jun 26, 2025Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton32 LF$95.00$1003
Jun 24, 2025Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson72 LF$100$1102
Apr 1, 2025Mill & Overlay approximately 4 miles of SR 15 from Queen Street to north of Audubon DriveJones104 LF$172$1723

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.