BidCrew Data / Mississippi / Prices / Guard Rail, Bridge End Section, Type H
MDOT pay item · 606-D019

Guard Rail, Bridge End Section, Type H: Mississippi winning bid prices

The low bidder priced guard rail, bridge end section, type h at a median $2,905 per each over the last 12 months (18 contracts), up 28% from the year before and up 65% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$2,905
18 contracts
Median, prior 12 months
$2,277
13 contracts
Median, 2020
$1,765
6 contracts
Winner vs. field
level with
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$1,500$2,000$2,500$3,000$3,5002020202120222023202420252026*$2,902
Price vs. quantityEvery winning price since 2020 (log scale)
$1,000$2,000$3,000$4,000110
Does quantity matter?Median winning price by quantity band
$0$1,000$2,000$3,000$2,570≤4$2,6634–6$2,7956–10$2,475>10

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Overlay approximately 7 miles of MS 48 from SR 24 to Magnolia Progress RoadPike4 EA$2,936$2,9163
Oct 27, 2026Fog Seal approximately 5 miles of I-59 from the Forrest County Line to the Forrest County Lamar, Forrest1 EA$3,260–1
Oct 27, 2026Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery6 EA$2,775–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin2 EA$3,671$3,6946
Sep 22, 2026Bridge Repair on SR 532 over Stream (Bridge No. 13.5)Covington4 EA$3,917$3,8586
Aug 25, 2026Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North of US 80/SR27 IntersecWarren6 EA$2,902$2,9023
Jul 28, 2026Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds16 EA$3,031$3,0313
Jun 23, 2026Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison8 EA$2,825$2,9132
Jun 5, 2026Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo2 EA$2,850–1
Jun 5, 2026Mill & Overlay approximately 9 miles of US 84 Westbound Lanes from Collins to the Jones CoCovington2 EA$2,487$2,9003
May 27, 2026Overlay approximately 11.4 miles of SR 15 from Ovett-Scarbrough Road to south of Tuckers CJones16 EA$2,971$2,7862
May 27, 2026Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee8 EA$2,595$2,5632
Apr 28, 2026Overlay approximately 11.2 miles on MS 550 from the Jefferson County Line to east of BouieLincoln8 EA$2,908$2,7503
Apr 28, 2026Ultra-Thin Overlay & Safety Improvements on approximately 8 miles of existing SR 482 from Neshoba12 EA$2,300$2,4264
Apr 10, 2026Pavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 4Yazoo10 EA$2,539$2,5393
Mar 24, 2026Mill & Overlay approximately 4.2 miles of US 84 from Bude to the Homochitto River BridgeFranklin12 EA$2,529$2,5253
Feb 24, 2026Seal & Overlay approximately 8.5 miles of MS 44 from near Gates Road to the Lamar County LMarion8 EA$3,445$3,4453
Oct 28, 2025Mill & Overlay approximately 6 miles on I-20 from Clinton to MS 18Hinds3 EA$3,057$3,0533
Aug 26, 2025Mill & Overlay approximately 19.5 miles of US 49W from Ruleville to the Coahoma County LinSunflower12 EA$3,674$3,6743
Jul 22, 2025Mill & Overlay approximately 8 miles on US 49 east from US 82 to 300 north of SR 442Leflore4 EA$2,174$2,1372

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.