The low bidder priced combination concrete curb and gutter type 3a at a median $47.50 per linear foot over the last 12 months (1 contracts), up 13% from the year before and up 94% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 259 LF | $47.50 | – | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 380 LF | $42.00 | $42.50 | 3 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 3.6K LF | $39.60 | $39.00 | 3 |
| Nov 26, 2024 | Intersection Improvements on US 49 at SR 35Covington | 266 LF | $59.60 | $58.00 | 3 |
| Oct 22, 2024 | Bridge Replacement on SR 12 over Moccasin Creek (Bridge No. 69.2)Holmes | 305 LF | $40.00 | $50.08 | 4 |
| Jun 25, 2024 | Intersection Improvements on USRankin | 1.2K LF | $45.00 | $47.25 | 2 |
| Jan 31, 2024 | Intersection Improvements on USDeSoto | 860 LF | $36.00 | $36.75 | 4 |
| Nov 2, 2023 | Bridge Replacements & Bank Stabilization on US 98 at the Pearl River (Bridge Nos. 118.5A &Marion | 26 LF | $90.00 | $87.50 | 2 |
| Oct 24, 2023 | Construction project, Sunflower CountySunflower | 350 LF | $51.25 | $46.88 | 2 |
| Oct 24, 2023 | Construction project, Harrison CountyHarrison | 2.4K LF | $32.00 | – | 1 |
| Jul 27, 2022 | Mill & Overlay approximately 3 miles of SR 22 from the Beginning of the 5-Lane Section to Madison | 561 LF | $60.00 | $62.50 | 4 |
| May 24, 2022 | Construction project, Copiah CountyCopiah | 699 LF | $27.25 | $29.63 | 2 |
| Mar 22, 2022 | Overlay approximatelyPanola | 662 LF | $53.00 | – | 1 |
| Aug 24, 2021 | Construction of a Roundabout on SRMarshall | 6.2K LF | $23.00 | $30.38 | 4 |
| Jun 22, 2021 | Safety Improvements along SRTishomingo | 2.1K LF | $25.00 | $45.00 | 5 |
| Apr 27, 2021 | Intersection Improvements on US 84 at Reservoir Road / Magnolia Hill Road & SR 184Wayne | 986 LF | $27.50 | – | 4 |
| Jan 26, 2021 | Overlay approximatelyNewton | 150 LF | $55.00 | $45.25 | 2 |
| Oct 27, 2020 | Construction project, Neshoba CountyNeshoba | 263 LF | $24.00 | $24.00 | 3 |
| Sep 22, 2020 | Construction project, Harrison CountyHarrison | 324 LF | $25.00 | $41.67 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.