The low bidder priced remove and reset signs, all sizes at a median $306 per each over the last 12 months (3 contracts), up 53% from the year before and down 24% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 1 EA | $730 | – | 1 |
| May 27, 2026 | Pavement Restoration of US 49 from the Hinds County Line to the Yazoo County Line, and ITSMadison, Hinds, Yazoo | 15 EA | $306 | $303 | 4 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 6 EA | $300 | $300 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 894 EA | $75.00 | $80.00 | 3 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 25 EA | $150 | $155 | 3 |
| May 28, 2025 | Mill & Overlay approximately 3 miles of SR 178 from North Access Road to Old SR 25Itawamba | 10 EA | $200 | $200 | 4 |
| Jan 28, 2025 | Wayne Installation of Ramp Gates on I-59 from the Louisiana State Line to north of US 84 &Lincoln, Pike, Forrest, Jones, Lamar, Pearl River, Adams | 2 EA | $500 | $500 | 3 |
| Jan 28, 2025 | Mill & Overlay approximately 7 miles of SR 16 from lane mile 13.195 to 0.5 miles east of tLeake, Neshoba | 2 EA | $1,445 | $1,445 | 2 |
| Oct 22, 2024 | Intersection Improvements on SR 25 at Mt. Helm Road and at Pisgah RoadRankin | 7 EA | $175 | $191 | 2 |
| Jul 30, 2024 | Pavement Restoration on approximately 11 miles of US 49 from 0.8 miles north of Old HighwaYazoo | 28 EA | $256 | $850 | 3 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 79 EA | $500 | $362 | 2 |
| Apr 2, 2024 | Construction project, Madison CountyMadison | 6 EA | $354 | $390 | 7 |
| Dec 5, 2023 | Bridge Replacement on US 11 at Hobolochitto Creek in Picayune (Bridge No. 11.3), known as Pearl River | 28 EA | $158 | $494 | 5 |
| Jul 25, 2023 | Overlay approximatelyPearl River | 1 EA | $1,000 | – | 1 |
| May 30, 2023 | Bridge Replacements on SR 397 between SRWinston | 7 EA | $125 | $127 | 2 |
| Apr 25, 2023 | Construction project, Wilkinson CountyWilkinson | 21 EA | $100 | $475 | 3 |
| Oct 5, 2022 | Construction project, Hinds CountyHinds | 4 EA | $500 | – | 1 |
| Sep 28, 2022 | Construction project, Jackson CountyJackson | 17 EA | $843 | $820 | 4 |
| Jan 25, 2022 | Bridge Replacement on SRGrenada | 1 EA | $1,300 | $1,081 | 6 |
| Jan 25, 2022 | Intersection Improvements on SR 826 at SR 14 & USSharkey | 5 EA | $1,500 | $810 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.