The low bidder priced delineators, post mounted, double white at a median $111 per each over the last 12 months (7 contracts), up 71% from the year before and up 93% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 99 EA | $60.00 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 152 EA | $137 | $137 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 54 EA | $141 | $141 | 6 |
| Jul 28, 2026 | Widening on I-10 at MS 605 WB RampHarrison | 23 EA | $111 | $98.33 | 3 |
| Jun 23, 2026 | Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison | 100 EA | $148 | $149 | 2 |
| Apr 28, 2026 | OGFC Lift approximately 5.3 miles on I-20 from MS 18 to US 80 (East Brandon)Rankin | 155 EA | $83.95 | $83.95 | 3 |
| Nov 25, 2025 | Mill & Overlay approximately 10 miles on US 45A from the Chickasaw County Line to the Lee Monroe | 115 EA | $48.00 | $48.00 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 68 EA | $145 | $145 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 9 miles of SR 346 from the beginning of State Maintenance to Pontotoc | 10 EA | $50.00 | $50.00 | 5 |
| Aug 26, 2025 | Mill & Overlay approximately 4.3 miles of I-55 Carroll Co from the Montgomery County Line Carroll, Montgomery | 37 EA | $65.00 | – | 1 |
| Jul 31, 2025 | Mill & Overlay approximately 14 miles of I-22 in Union County from the junction at SR 30 tUnion, Pontotoc | 287 EA | $50.00 | $50.00 | 2 |
| May 28, 2025 | Remove & Replace OGFC Lift on approximately 2 miles of I-220 from the Hinds County Line toMadison, Hinds | 350 EA | $130 | $130 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 78 EA | $56.93 | – | 1 |
| Feb 25, 2025 | Remove & Replace approximately 13 miles of OGFC on I-20 from East Brandon to the Scott CouRankin | 18 EA | $90.00 | $90.00 | 3 |
| Jan 28, 2025 | Wayne Installation of Ramp Gates on I-59 from the Louisiana State Line to north of US 84 &Lincoln, Pike, Forrest, Jones, Lamar, Pearl River, Adams | 21 EA | $65.00 | $65.00 | 3 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 6 EA | $73.00 | $73.00 | 3 |
| Nov 26, 2024 | Mill & Overlay approximately 5 miles of I-22 from the Union County Line to the Belden ExitLee, Pontotoc | 264 EA | $45.00 | $45.00 | 3 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 51 EA | $86.00 | $88.00 | 2 |
| Mar 26, 2024 | Pavement Restoration of approximately 5 miles of I-55 from SR 24 to US 98 & Roundabout ConPike | 240 EA | $104 | $99.25 | 2 |
| Dec 5, 2023 | Widening of I-10 from Diamondhead to County Farm Road, Installation of ITS Components fromHancock, Harrison | 500 EA | $120 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.