The low bidder priced traffic signal conduit, underground, type 4, 2" at a median $11.00 per linear foot over the last 12 months (6 contracts), down 8% from the year before and up 27% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 160 LF | $12.65 | $17.00 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 725 LF | $4.50 | $4.78 | 6 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 940 LF | $12.00 | $12.00 | 3 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 240 LF | $13.00 | $13.00 | 5 |
| Jun 5, 2026 | Mill & Overlay approximately 3 miles of MS 16/149 from MS 3 to US 49Yazoo | 100 LF | $1.00 | – | 1 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 4.2K LF | $10.00 | $10.00 | 2 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 1.3K LF | $15.00 | $15.00 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 14K LF | $9.00 | $9.55 | 3 |
| Jul 22, 2025 | Mill & Overlay approximately 3 miles of US 98 from 400 feet west of Weathersby Drive to thLamar, Forrest | 50 LF | $57.00 | $55.00 | 2 |
| Jun 24, 2025 | Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson | 1.5K LF | $14.00 | $13.30 | 2 |
| Apr 22, 2025 | Intersection Improvements on US 49 from Desoto Park Road to 500' south of East Wortham RoaHarrison | 269 LF | $10.00 | $11.00 | 2 |
| Nov 26, 2024 | Intersection Improvements on US 49 at SR 35Covington | 212 LF | $1.30 | $1.20 | 3 |
| Sep 25, 2024 | Construction project, Pontotoc CountyPontotoc | 133 LF | $25.00 | – | 1 |
| Jul 11, 2024 | Construction project, Madison CountyMadison | 229 LF | $34.34 | $34.49 | 3 |
| Jun 11, 2024 | Construction project, Lafayette CountyLafayette | 350 LF | $12.00 | $16.25 | 5 |
| May 29, 2024 | Traffic Signal Installation on US 49W at SRSunflower | 135 LF | $17.00 | $14.50 | 2 |
| Jan 31, 2024 | Intersection Improvements on USDeSoto | 200 LF | $13.70 | $6.59 | 4 |
| Jan 24, 2024 | Construction project, Hinds CountyHinds | 200 LF | $25.00 | $26.50 | 2 |
| Jan 24, 2024 | Intersection Improvements at SRSmith | 135 LF | $12.00 | $12.00 | 5 |
| Jan 24, 2024 | Construction project, Harrison CountyHarrison | 275 LF | $12.77 | – | 1 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.