The low bidder priced 12.5-mm, st, asphalt pavement at a median $180 per ton over the last 12 months (16 contracts), down 2% from the year before and up 64% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$180
16 contracts
Median, prior 12 months
$184
9 contracts
Median, 2020
$110
17 contracts
Winner vs. field
2% below
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$100$150$200$2502020202120222023202420252026*$187
Price vs. quantityEvery winning price since 2020 (log scale)
$0$200$400$600$800101001.0K10K
Does quantity matter?Median winning price by quantity band
$0$100$200$300$300≤232$187232–959$165959–3.8K$127>3.8K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Mill & Overlay approximately 13.7 miles of I-59 from 0.5 miles north of the McNeil Exit toPearl River90 TON$325–1
Oct 27, 2026Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren652 TON$226$2353
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson313 TON$194–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin4.5K TON$168$1766
Sep 1, 2026Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie2.3K TON$173$1776
Aug 25, 2026Bridge Replacement on SR 486 (Bridge No. 1.0)Neshoba96 TON$265$2924
Jul 28, 2026Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds125 TON$343$3843
May 27, 2026Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake618 TON$192$1968
May 27, 2026Bridge Replacement on SR 15 over Cypress Branch on Bridge No. 15.7Harrison284 TON$187$1855
May 27, 2026Pavement Restoration of US 49 from the Hinds County Line to the Yazoo County Line, and ITSMadison, Hinds, Yazoo6.8K TON$122$1234
Apr 28, 2026Ultra-Thin Overlay & Safety Improvements on approximately 8 miles of existing SR 482 from Neshoba1.3K TON$165$2334
Apr 28, 2026OGFC Lift on I-55 from the Mississippi State Line to MS 568Pike14 TON$300$3952
Apr 10, 2026Pavement Restoration on US 49 from Madison County Line to 0.8 miles North of Old Highway 4Yazoo11K TON$113$1213
Feb 24, 2026Mill & Overlay approximately 3 miles of MS 487 from east of Tuscolameta Big Canal to SR 35Leake5.0K TON$133$1355
Feb 24, 2026Mill & Overlay approximately 3.4 miles of SR 854 from SR 39 to the Naval Air StationLauderdale1.8K TON$173$1753
Nov 25, 2025Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith1.2K TON$152$1507
Sep 23, 2025Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette3.8K TON$173$1733
Jun 26, 2025Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton5.0K TON$173$1753
Jun 24, 2025Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson50 TON$233$3162
Feb 25, 2025Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson959 TON$162$1705

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.