The low bidder priced 9.5-mm, mt, asphalt pavement at a median $159 per ton over the last 12 months (26 contracts), up 9% from the year before and up 64% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 6.0K TON | $133 | $141 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 829 TON | $174 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 2.6K TON | $195 | $185 | 6 |
| Sep 22, 2026 | Mill & Overlay approximately 2.5 miles of US 49 from SR 1 to the Isle of Capri ParkwayCoahoma | 3.0K TON | $215 | – | 1 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 1.1K TON | $192 | $192 | 3 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 1.6K TON | $166 | $182 | 3 |
| Jun 23, 2026 | Widen & Overlay approximately 2 miles of SR 26 from the east end of the Pearl River BridgePearl River | 14K TON | $130 | – | 1 |
| Jun 23, 2026 | Mill & Overlay approximately 3.87 miles of SR 149 from US 49S to US 49NStone | 7.8K TON | $140 | $139 | 2 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 1.2K TON | $178 | $204 | 6 |
| Jun 12, 2026 | Emergency Slide Repair on SR 178 approximately 0.66 miles south of CR 121Union | 40 TON | $578 | $494 | 4 |
| Jun 5, 2026 | Mill & Overlay approximately 9 miles of SR 25 from US 45A to US 45Monroe | 14K TON | $159 | $169 | 2 |
| Jun 5, 2026 | Overlay approximately 14.3 miles of MS Highway 7 beginning at the Lafayette County Line goMarshall | 24K TON | $141 | – | 1 |
| May 27, 2026 | Widening of US 51 from Glenwild to North StreetGrenada | 18K TON | $160 | $154 | 2 |
| May 27, 2026 | Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the JuTishomingo | 15K TON | $148 | $149 | 2 |
| May 27, 2026 | Mill & Overlay approximately 7 miles of SR 4 from east of Church Street to west of the JunPrentiss | 11K TON | $145 | $153 | 2 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 1.6K TON | $170 | $187 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 15K TON | $133 | $135 | 3 |
| Apr 28, 2026 | Overlay approximately 14.5 miles on US 98 from 1.05 miles east of SR 29 to the Greene CounPerry | 7.5K TON | $135 | $150 | 2 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 1.3K TON | $194 | $166 | 4 |
| Apr 10, 2026 | Mill & Overlay approximately 7 miles of US 82 from 1 mile east of Military Road to the AlaLowndes | 2.8K TON | $155 | $159 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.