The low bidder priced 12.5-mm, mt, asphalt pavement, leveling at a median $185 per ton over the last 12 months (5 contracts), up 9% from the year before and up 38% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 88 TON | $186 | $344 | 6 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 1.0K TON | $173 | $202 | 6 |
| May 27, 2026 | Thin Lift Overlay of MS 16 from Thompson Drive to the Intersection of MS 15Neshoba | 10 TON | $475 | $350 | 5 |
| May 27, 2026 | Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 mileLeake | 525 TON | $185 | $183 | 4 |
| Feb 24, 2026 | Mill & Overlay approximately 9.8 miles of SR 25 from Renfroe to the Attala County LineLeake | 1.8K TON | $160 | $166 | 5 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 106 TON | $267 | $267 | 3 |
| Apr 30, 2025 | Mill & Overlay & Concrete Rehabilitation on approximately 2 miles of SR 25 from the BOSM tHinds | 136 TON | $166 | $166 | 3 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 1.3K TON | $156 | $151 | 2 |
| Feb 25, 2025 | Mill & Overlay approximately 9 miles of US 51 from the Madison City Limits to Dinkins StreMadison | 2.9K TON | $144 | $142 | 2 |
| Jan 28, 2025 | Overlay approximately 10 miles of SR 43 from SR 481 to the Madison County LineRankin | 3.0K TON | $159 | $156 | 4 |
| Jan 28, 2025 | Mill & Overlay approximately 7 miles of SR 16 from lane mile 13.195 to 0.5 miles east of tLeake, Neshoba | 154 TON | $250 | $235 | 2 |
| Dec 5, 2024 | Mill & Overlay approximately 2 miles of SR 16 through the City of PhiladelphiaNeshoba | 838 TON | $181 | $190 | 5 |
| Nov 26, 2024 | Roundabout Improvements on Old Brandon Road at Airport Road, International Drive, & SR 475Rankin | 692 TON | $170 | $167 | 4 |
| Nov 26, 2024 | Mill & Overlay approximately 13 miles of SR 16 from the Neshoba County Line to east of WatKemper | 130 TON | $171 | $181 | 5 |
| Sep 4, 2024 | Construction project, Madison CountyMadison | 150 TON | $246 | $246 | 3 |
| Jul 23, 2024 | Construction project, Leake CountyLeake | 442 TON | $201 | $221 | 2 |
| Jun 11, 2024 | Construction project, Lafayette CountyLafayette | 657 TON | $220 | $238 | 5 |
| Apr 23, 2024 | Mill & Overlay approximately 9.5 miles of SR 469 from Florence to SR 468Rankin | 292 TON | $200 | $212 | 4 |
| Apr 23, 2024 | Mill & Overlay approximately 7 miles of SR 21 from Steele to SebastopolScott | 490 TON | $186 | $196 | 2 |
| Mar 5, 2024 | Construction project, Kemper CountyKemper | 150 TON | $245 | $506 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.