Mississippi highway lettings: the state of the market

Every MDOT contract let since 2020: how much work there is, where it is, who wins it, what it costs, and what is coming next. Built for the people who decide what a highway contractor bids.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Awarded, last 12 months
$1.05B
up 5% vs. prior 12 months
Contracts let
160
prior 12 months: 147
Bidders per contract
3.70
prior 12 months: 3.05
Single-bid contracts
13%
prior 12 months: 12%
Low bid vs. MDOT estimate
−4.9%
median, last 12 months
Low-to-second gap
$55.5M
median 6.9% per contract
The brief

Nine things to know before the next letting

  1. Market size

    $1.05B awarded in the last 12 months

    160 contracts, up 5% in dollars from the 12 months before ($1.00B on 147 contracts). The median contract is $3.0M.

  2. Competition

    3.70 bidders per contract, up from 3.05

    The field was thinnest in 2022: 2.34 bidders a contract and 37% of contracts drew one bid. In the last 12 months, 13% were single-bid.

  3. Price of competition

    Each extra bidder takes about 4.0% off the low bid

    Single-bid contracts landed a median 7% above MDOT's estimate; with six or more bidders, 14% below. Knowing who will show up is worth more than any unit price.

  4. Prices

    Winning prices are 47% above 2020–21

    The BidCrew Mississippi Bid Price Index (188 pay items) peaked at 147 in 2026 and stands at 147. Superpave 9.5-mm ST asphalt went from $97.24 a ton in 2020 to $157 in the last 12 months.

  5. Who wins

    Three firms took 32% of the dollars in three years

    APAC - Mississippi, Inc. (13%), T. L. Wallace Construction, Inc. (11%), W. G. Yates & Sons Construction Company (9%). 137 firms won at least one contract.

  6. Money on the table

    $55.5M separated the low and second bids

    That is the last 12 months. The median gap between first and second was 6.9%, down from 10.0% the year before as fields grew.

  7. Where the work is

    Newton (District 5) let $896M in three years

    The most of any district. The thinnest fields are in District 6 (Hattiesburg): 2.49 bidders a contract and 18% single-bid.

  8. Thrown out

    84 sets of bids were rejected and re-let

    Since 2020. 60% were single-bid, with low bids a median 24% above the estimate. Re-letting rarely saved money: the new low bid came in a median 0.8% lower, and the same firm won again 60% of the time.

  9. What's next

    251 projects on MDOT's proposed letting list

    Through October 2027. 93 are overlay and resurfacing, 86 are bridge work. The busiest month is January 2027 with 47 projects.

Map

Where the work is

Counties shaded by what MDOT let there. Pick a district to zoom in, then a county to see who won its work. Contracts that span several counties count in each, with the dollars split between them.

01 · Market size

$853M a year, and lumpy

MDOT let $853M a year on average from 2020 through 2025. The total swings with a handful of large jobs: in the last three years, contracts of $20 million and up were 6% of the count and 50% of the dollars.

Dollars awarded by quarterLow bid of every MDOT contract. Hover for detail.
$0$100M$200M$300M$400M2020202120222023202420252026
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.
When MDOT lets workAverage dollars let in each calendar month, 2020–2025
$0$20M$40M$60M$80M$100MJanFebMarAprMayJunJulAugSepOctNovDec

By contract size, last 3 years

Contract sizeContractsAwardedBidders / contractSingle-bidLow vs. estimateGap to 2nd
Under $1M102$54.0M3.4713%−8.0%10.5%
$1M–$5M215$598M3.1910%−8.8%9.7%
$5M–$20M111$998M2.8822%−4.6%4.4%
$20M and up25$1.65B2.8016%+5.3%7.9%
02 · Competition

The field is back, and it is pricing the work down

Bidders per contract fell to 2.34 in 2022, when 37% of contracts drew a single bid and low bids ran a median 0.6% above MDOT's estimate. Since then the field has rebuilt to 3.62 in 2026 so far.

Bidders per contractAverage across contracts let each year
0.01.02.03.04.02020202120222023202420252026*3.62
Contracts with a single bidShare of contracts let each year
0%10%20%30%40%2020202120222023202420252026*14%

More bidders means lower prices, and the effect is steady: across 1,003 contracts, each additional bidder lowers the low bid by about 4.0% relative to the estimate.

Low bid vs. MDOT's estimate, by number of biddersMedian, all contracts since 2020
−15%−10%−5%0%+5%+10%+7.1%1−3.8%2−8.9%3−10.1%4−10.1%5−13.7%6+
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew.

Competition by type of work, last 3 years

Work typeContractsAwardedMedian sizeBidders / contractSingle-bidLow vs. estimateGap to 2nd
Overlay & resurfacing184$1.00B$4.2M2.6716%−8.2%6.6%
Construction & widening112$1.13B$1.8M3.1312%−7.5%10.6%
Bridge repair & rehab89$506M$1.0M4.078%−4.5%9.7%
Bridge replacement26$413M$8.1M4.508%−2.3%5.7%
Intersections & safety30$232M$3.0M2.4327%−5.6%6.1%
Buildings & other12$18.9M$922K2.9225%+7.3%15.3%
03 · Who wins

A concentrated market at the top, an open one below it

Over the last three years 137 firms won at least one MDOT contract, but the top three took 32% of the dollars. Large jobs drive most of that: a single interstate or bridge contract can move a firm's share by several points in a year.

Share of dollars awardedLast 3 years, top 12 firms
0%5%10%15%APAC - Mississippi, Inc.13.0%T. L. Wallace Construction, Inc.10.6%W. G. Yates & Sons Construction C…8.8%Huey P Stockstill, LLC8.3%Talbot Brothers Contracting Co., …6.8%Lehman-Roberts Company4.3%Eutaw Construction Company, Inc.4.2%Cotton Creek Transport, Inc.3.7%Hemphill Construction Company, In…3.2%Dickerson & Bowen, Inc.2.9%Key, LLC2.7%Warren Paving, Inc.2.6%
Top three firms' shareShare of each year's awarded dollars
0%20%40%60%80%2020202120222023202420252026*47%

Win rates, head-to-head records and district leaders →

04 · Money on the table

$55.5M between first and second in a year

The gap between the low bid and the second bid is what the winner could have added and still won. Over the last three years the median gap was 8.6%; a quarter of contracts were decided by less than 3.5%.

How close the low bids wereContracts by gap between low and second bid (%), last 3 years
020406080600512384376338271024121414171610188020+
Dollars between low and second bidSum across contracts let each year
$0$50M$100M$150M$30.3M2020$61.4M2021$62.3M2022$67.5M2023$104M2024$115M2025$50.1M2026*
05 · Thrown out

When MDOT rejects the bids, the price rarely moves

When a project comes back to a later letting within 18 months, MDOT rejected the first set of bids. That happened 84 times since 2020, on $666M of low bids, and 60% of them drew a single bid. On re-letting, the field grew from 1.8 to 2.0 bidders on average, yet the new low bid came in a median 0.8% lower and the same firm won again 60% of the time. Rejected attempts are left out of every other total on this site.

Bid sets rejected and re-letBy year of the rejected letting
0102030920201520212420224202311202412202592026*

Most recent

RejectedContractLow bidRe-let
Aug 25, 2026Add 2 Lanes to I-55 from SR 463 to Gluckstadt Road, & Mill & Overlay aMadison · 3 bids$196M$188M Oct 27, 2026 · −4%
Aug 25, 2026Bridge Repair over MS 19 over Big Black River (Bridge No. 114.9)Attala · 4 bids$1.7M$1.8M Oct 27, 2026 · +9%
Jul 28, 2026Bridge Replacement on SR 28 between Copiah County Line & Pinola (BridgSimpson · 4 bids$25.1M$27.4M Oct 27, 2026 · +9%
Jun 5, 2026Mill & Overlay approximately 11 miles of US 61 from 0.5 miles North ofWarren · 1 bid$12.0M$12.2M Aug 25, 2026 · +2%
May 27, 2026Widening on I-10 at MS 605 WB RampHarrison · 3 bids$1.4M$1.4M Jul 28, 2026 · −2%
May 27, 2026Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning ofHinds · 3 bids$4.9M$4.3M Jul 28, 2026 · −11%
Apr 28, 2026Overlay approximately 6.2 miles of I-59 from north of CR 39 to the ClaJasper · 2 bids$3.7M$5.8M Oct 27, 2026 · +56%
Feb 3, 2026Bridge Replacement on SR 486 (Bridge No. 1.0) Withdrawn from Letting 2Neshoba · 1 bid$3.4M$2.4M Aug 25, 2026 · −29%
06 · Prices

Prices jumped in 2022 and have not come back down

The BidCrew Mississippi Bid Price Index tracks the median winning unit price of 188 pay items bid every year since 2020, weighted by dollars. It rose 25% in 2022 alone and is 47% above its 2020–21 level.

Mississippi Bid Price Index2020–21 = 100
801001201401602020202120222023202420252026*2020–21 = 100147
Superpave 9.5-mm ST asphaltWinning price per ton: median and middle half
$50$100$150$200$2502020202120222023202420252026*$153

Biggest pay items, last 12 months

Pay itemUnitMedian, last 12 movs. year earlier2020 medianContracts
9.5-mm, ST, Asphalt Pavement403-A015 / 907-403-A015TON$157+5%$97.2450
9.5-mm, MT, Asphalt Pavement403-A014 / 907-403-A014TON$159+9%$97.0026
Stone Matrix Asphalt, 9.5 mm Mixture907-405-A001TON$180−3%–15
Fine Milling of Bituminous Pavement, All Depths406-D001SY$4.58+35%$2.4590
12.5-mm, MT, Asphalt Pavement403-A002 / 907-403-A002TON$168+13%$10112
Size 610 Crushed Stone Base304-F002TON$86.53+16%$60.0034
19-mm, ST, Asphalt Pavement403-A006 / 907-403-A006TON$160−10%$12333
Open Graded Friction Course, 9.5-mm Mixture402-A002 / 907-402-A002TON$198+5%$1219
9.5-mm, HT, Asphalt Pavement403-A013 / 907-403-A013TON$178+5%$11418
Ultra Thin Asphalt Pavement907-411-A001TON$128−2%$77.7113

All 562 pay items with price history →

07 · What's next

251 projects on MDOT's list for the next 12 months

MDOT publishes a rolling schedule of the projects it expects to let. It carries no cost estimates, but it tells you what kind of work is coming and where. Listed as of Nov 21, 2026.

Projects by proposed letting monthMDOT Proposed Letting schedule
020406039Nov ’263Dec47Jan ’2717Feb15Mar20Apr16May24Jun23Jul10Aug16Sep21Oct
Source: MDOT Schedule of Proposed Projects, Nov 21, 2026.

The full list, by district and type →

08 · Latest letting

October 27, 2026: 15 contracts, $347M

2.20 bidders per contract; low bids a median 4.8% above MDOT's estimate. The largest was Construction project, Madison County ($188M, T. L. Wallace Construction, Inc., 3 bidders).

Full results → · Every letting since 2020 →

09 · Districts

Six districts, six different markets

About this data