BidCrew Data / Mississippi / Prices / 12.5-mm, MT, Asphalt Pavement
MDOT pay item · 403-A002 / 907-403-A002

12.5-mm, MT, Asphalt Pavement: Mississippi winning bid prices

The low bidder priced 12.5-mm, mt, asphalt pavement at a median $168 per ton over the last 12 months (12 contracts), up 13% from the year before and up 67% since 2020.

Data through the October 27, 2026 letting · Refreshed November 21, 2026

Median, last 12 months
$168
12 contracts
Median, prior 12 months
$149
18 contracts
Median, 2020
$101
14 contracts
Winner vs. field
4% below
winning price vs. all bidders' median
Winning price by yearMedian and middle half of the low bidder's unit price
$50$100$150$200$2502020202120222023202420252026*$168
Price vs. quantityEvery winning price since 2020 (log scale)
$0$100$200$300$400101001.0K10K
Does quantity matter?Median winning price by quantity band
$0$50$100$150$200$250$215≤769$168769–2.4K$1262.4K–18K$128>18K

The last 20 winning prices

LetContractQuantityWinning priceAll bidders' medianBidders
Oct 27, 2026Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin3.6K TON$125$1414
Oct 27, 2026Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson554 TON$159–1
Sep 29, 2026Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin2.0K TON$177$1836
Sep 1, 2026Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike550 TON$219$2193
Jul 28, 2026Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke2.4K TON$180$1982
Jul 28, 2026Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest3.1K TON$164$1773
Jun 23, 2026Roundabout on US 51 at Green T RoadDeSoto984 TON$173$2026
May 27, 2026Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 mileLeake21K TON$143$1494
May 27, 2026Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin1.2K TON$148$1632
Apr 28, 2026I-10 Jackson County Welcome CenterJackson2.0K TON$180$1564
Feb 24, 2026Mill & Overlay approximately 9.8 miles of SR 25 from Renfroe to the Attala County LineLeake47K TON$127$1315
Feb 3, 2026Slide Repair on US 61 Southbound across from Fire Tower RoadAdams71 TON$220$2054
Sep 23, 2025Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette27K TON$126$1263
Jul 31, 2025Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison29K TON$135$1523
Jul 22, 2025Thin Lift & Overlay approximately 16 miles of SR 43 from just south of Wheats Curve to thePearl River26 TON$225$2382
Jun 25, 2025Bridge Repair on SR 43 over the Pearl River Relief (Bridge No. 183.8)Madison3 TON$1,500$3,2502
May 28, 2025Mill & Overlay approximately 4 miles of SR 485 from SR 15 to SR 21Neshoba7.5K TON$119$1524
Apr 22, 2025Bridge Repair on US 80 over Pearl River Relief (Bridge No. 46.9)Rankin17 TON$600–1
Apr 22, 2025Intersection Improvements on US 49 from Desoto Park Road to 500' south of East Wortham RoaHarrison110 TON$255$2512
Apr 1, 2025Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba2.3K TON$220$2212

Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.