The low bidder priced 12.5-mm, mt, asphalt pavement at a median $168 per ton over the last 12 months (12 contracts), up 13% from the year before and up 67% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 3.6K TON | $125 | $141 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 554 TON | $159 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 2.0K TON | $177 | $183 | 6 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 550 TON | $219 | $219 | 3 |
| Jul 28, 2026 | Micro-Surface approximately 14 miles of SR 512 & SR 513Clarke | 2.4K TON | $180 | $198 | 2 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 3.1K TON | $164 | $177 | 3 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 984 TON | $173 | $202 | 6 |
| May 27, 2026 | Traffic Signal Improvements on MS 16 at Van Buren, and Mill & Overlay approximately 6 mileLeake | 21K TON | $143 | $149 | 4 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 1.2K TON | $148 | $163 | 2 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 2.0K TON | $180 | $156 | 4 |
| Feb 24, 2026 | Mill & Overlay approximately 9.8 miles of SR 25 from Renfroe to the Attala County LineLeake | 47K TON | $127 | $131 | 5 |
| Feb 3, 2026 | Slide Repair on US 61 Southbound across from Fire Tower RoadAdams | 71 TON | $220 | $205 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 27K TON | $126 | $126 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 29K TON | $135 | $152 | 3 |
| Jul 22, 2025 | Thin Lift & Overlay approximately 16 miles of SR 43 from just south of Wheats Curve to thePearl River | 26 TON | $225 | $238 | 2 |
| Jun 25, 2025 | Bridge Repair on SR 43 over the Pearl River Relief (Bridge No. 183.8)Madison | 3 TON | $1,500 | $3,250 | 2 |
| May 28, 2025 | Mill & Overlay approximately 4 miles of SR 485 from SR 15 to SR 21Neshoba | 7.5K TON | $119 | $152 | 4 |
| Apr 22, 2025 | Bridge Repair on US 80 over Pearl River Relief (Bridge No. 46.9)Rankin | 17 TON | $600 | – | 1 |
| Apr 22, 2025 | Intersection Improvements on US 49 from Desoto Park Road to 500' south of East Wortham RoaHarrison | 110 TON | $255 | $251 | 2 |
| Apr 1, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 2.3K TON | $220 | $221 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.