The low bidder priced removal of flared end section, all sizes at a median $500 per each over the last 12 months (7 contracts), down 50% from the year before and down 13% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 5 EA | $345 | $500 | 3 |
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 6 EA | $500 | $537 | 4 |
| Oct 27, 2026 | Mill & Overlay approximately 17 miles of I-22 beginning 1 mile west of the Landfill Road EMarshall | 1 EA | $1,543 | $1,250 | 4 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 20 EA | $343 | $858 | 6 |
| Jul 28, 2026 | Thin Lift Overlay approximately 10.2 miles of MS 467 from beginning of maintenance to SoutHinds | 2 EA | $4,500 | $4,500 | 3 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 7 EA | $500 | $1,113 | 6 |
| Nov 25, 2025 | Ditch Repair on I-20 near the Springridge Road InterchangeHinds | 1 EA | $1,314 | $1,100 | 5 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 10 EA | $1,000 | $1,000 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 17 EA | $700 | $700 | 3 |
| Apr 1, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 1 EA | $500 | $540 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 7 EA | $1,500 | – | 1 |
| Feb 25, 2025 | Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson | 13 EA | $1,330 | $558 | 5 |
| Feb 4, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 1 EA | $550 | – | 1 |
| Jan 28, 2025 | Wayne Installation of Ramp Gates on I-59 from the Louisiana State Line to north of US 84 &Lincoln, Pike, Forrest, Jones, Lamar, Pearl River, Adams | 1 EA | $4,500 | $4,500 | 3 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 2 EA | $1,360 | $985 | 3 |
| Nov 26, 2024 | Pearl River Installation of Median Cable Barrier & Bridge Pier Protection along I-59 from Clarke, Jasper | 3 EA | $1,000 | – | 1 |
| Oct 22, 2024 | Construction of a Roundabout on SR 3 at Willie Morris ParkwayYazoo | 6 EA | $750 | – | 1 |
| Oct 22, 2024 | Bridge Repair on I-20 over the Big Black River & Reliefs (Bridge Nos. 17.3A, 17.3B, 17.7A,Hinds, Warren | 2 EA | $1,070 | $1,348 | 2 |
| Jul 30, 2024 | Pavement Restoration on approximately 11 miles of US 49 from 0.8 miles north of Old HighwaYazoo | 2 EA | $1,500 | $1,500 | 3 |
| Jul 16, 2024 | Emergency Removal & Replacement of existing pipe located on SRPearl River | 1 EA | $265 | $750 | 4 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.