The low bidder priced 19-mm, mt, asphalt pavement at a median $173 per ton over the last 12 months (15 contracts), down 12% from the year before and up 38% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Slide Improvement on US 84 from west of Fire Tower Road to east of Providence RoadFranklin | 3.9K TON | $116 | $132 | 4 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 1.5K TON | $144 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 1.3K TON | $173 | $185 | 6 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 1.1K TON | $181 | $181 | 3 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 1.3K TON | $157 | $178 | 6 |
| Jun 12, 2026 | Emergency Slide Repair on SR 178 approximately 0.66 miles south of CR 121Union | 50 TON | $600 | $505 | 4 |
| Jun 5, 2026 | Mill & Overlay approximately 9 miles of SR 25 from US 45A to US 45Monroe | 1.5K TON | $220 | $212 | 2 |
| May 27, 2026 | Scrub Seal & Overlay approximately 12 miles of MS 172 from the junction of US 72 to the JuTishomingo | 50 TON | $150 | $153 | 2 |
| May 27, 2026 | Mill & Overlay approximately 7 miles of SR 4 from east of Church Street to west of the JunPrentiss | 250 TON | $185 | $181 | 2 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 1.5K TON | $145 | $159 | 2 |
| May 8, 2026 | Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay SprJasper | 216 TON | $189 | $200 | 3 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 2.8K TON | $171 | $146 | 4 |
| Mar 24, 2026 | Mill & Overlay approximately 3 miles of SR 145 from beginning of 4-lane section near CedarPrentiss | 335 TON | $183 | $191 | 2 |
| Feb 3, 2026 | Slide Repair on US 61 Southbound across from Fire Tower RoadAdams | 99 TON | $190 | $183 | 4 |
| Oct 28, 2025 | Overlay approximately 6 miles on SR 28 from Mize to Taylorsville, known as Project No. SP-Smith | 657 TON | $170 | $167 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 31K TON | $123 | $123 | 3 |
| Aug 26, 2025 | Mill & Overlay approximately 3.5 miles of US 45 from the beginning of the 4-Lane divided sMonroe | 1.1K TON | $165 | $190 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 26K TON | $128 | $153 | 3 |
| Jun 25, 2025 | Bridge Repair on SR 43 over the Pearl River Relief (Bridge No. 183.8)Madison | 5 TON | $1,500 | $3,250 | 2 |
| May 28, 2025 | Overlay approximately 8 miles of US 84 from Chambers Road to Middle Fork CreekFranklin | 883 TON | $123 | $129 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.