The low bidder priced concrete curb, special design at a median $68.45 per linear foot over the last 12 months (7 contracts), up 10% from the year before and up 96% since 2021.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 972 LF | $41.00 | $66.50 | 6 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 180 LF | $68.45 | $68.45 | 3 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 51 LF | $55.00 | $100 | 5 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 377 LF | $71.00 | $67.00 | 6 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 32 LF | $95.00 | $91.25 | 2 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 696 LF | $75.00 | $76.88 | 2 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 1.1K LF | $51.50 | $52.79 | 2 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 1.7K LF | $55.00 | $55.00 | 3 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 948 LF | $62.40 | $61.50 | 3 |
| Jul 31, 2025 | Safety Improvements on MS 67 from US 49 to the I-10 "Superstreets" CorridorHarrison | 3.4K LF | $40.00 | $40.00 | 3 |
| Apr 22, 2025 | Intersection Improvements on US 49 from Desoto Park Road to 500' south of East Wortham RoaHarrison | 90 LF | $47.75 | $47.63 | 2 |
| Apr 1, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 701 LF | $90.00 | $98.10 | 2 |
| Mar 25, 2025 | Concrete Pavement Rehabilitation on approximately 2.3 miles of US 82 through IndianolaSunflower | 284 LF | $59.00 | $59.00 | 3 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 590 LF | $70.00 | $72.50 | 2 |
| Feb 4, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 701 LF | $106 | – | 1 |
| Dec 5, 2024 | Mill & Overlay approximately 2 miles of SR 16 through the City of PhiladelphiaNeshoba | 150 LF | $104 | $104 | 5 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 2.0K LF | $41.25 | $66.85 | 3 |
| Nov 26, 2024 | Roundabout Improvements on Old Brandon Road at Airport Road, International Drive, & SR 475Rankin | 496 LF | $81.00 | $81.63 | 4 |
| Oct 22, 2024 | Safety Improvements along US 49 from WSF Tatum Blvd. to Sims RoadForrest | 4.4K LF | $39.25 | $42.88 | 2 |
| Oct 22, 2024 | Intersection Improvements on SR 25 at Mt. Helm Road and at Pisgah RoadRankin | 226 LF | $52.55 | $62.40 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.