The low bidder priced combination concrete curb and gutter type 2 modified at a median $38.40 per linear foot over the last 12 months (9 contracts), down 6% from the year before and up 43% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 1.8K LF | $44.85 | $44.85 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 12K LF | $32.50 | $38.25 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 3.1K LF | $47.50 | – | 4 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 1.3K LF | $38.40 | $36.00 | 3 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 135 LF | $61.00 | $61.00 | 5 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 69 LF | $54.50 | $58.75 | 6 |
| May 27, 2026 | Restricted Crossing U-Turn (RCUT) on US 84 at MS 33Franklin | 3.7K LF | $26.00 | $34.50 | 2 |
| Apr 28, 2026 | I-10 Jackson County Welcome CenterJackson | 207 LF | $29.45 | $41.83 | 4 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 4.0K LF | $37.40 | $35.40 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 2.2K LF | $39.25 | $40.00 | 3 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 693 LF | $40.00 | $44.60 | 3 |
| Jun 24, 2025 | Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson | 330 LF | $67.00 | $73.50 | 2 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 4.1K LF | $41.00 | $42.50 | 2 |
| Feb 25, 2025 | Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson | 2.6K LF | $44.75 | $45.00 | 5 |
| Oct 22, 2024 | Bridge Replacements on SR 346 over Mud Creek & Ditch (Bridge Nos. 3.6 & 3.8)Pontotoc | 126 LF | $75.00 | $70.00 | 4 |
| Jun 25, 2024 | Intersection Improvements on USRankin | 893 LF | $40.00 | $41.25 | 2 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 6.6K LF | $36.00 | $37.45 | 2 |
| Jan 24, 2024 | Construction of a Roundabout on USTate | 35 LF | $100 | $71.70 | 2 |
| Jan 24, 2024 | Construction project, Harrison CountyHarrison | 313 LF | $44.00 | – | 1 |
| Dec 5, 2023 | Add 2 Lanes on US 49 from O'Neal Road to north of School Road, known as Federal Aid ProjecHarrison | 1.5K LF | $44.11 | $42.05 | 2 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.