The low bidder priced right-of-way marker at a median $473 per each over the last 12 months (10 contracts), up 15% from the year before and up 91% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 3 EA | $525 | $525 | 3 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 44 EA | $708 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 20 EA | $495 | $448 | 6 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 60 EA | $384 | $420 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 26 EA | $400 | $413 | 6 |
| Aug 25, 2026 | SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee | 8 EA | $450 | $410 | 8 |
| Jun 23, 2026 | Roundabout on US 51 at Green T RoadDeSoto | 15 EA | $400 | $400 | 6 |
| May 27, 2026 | Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake | 28 EA | $590 | $449 | 8 |
| Feb 3, 2026 | Slide Repair on US 61 Southbound across from Fire Tower RoadAdams | 5 EA | $1,000 | $1,000 | 4 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 44 EA | $444 | $444 | 7 |
| Sep 23, 2025 | Bridge Replacement on SR 704 (Bridge No. 162.5)Benton | 9 EA | $400 | $428 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 338 EA | $350 | $350 | 3 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 232 EA | $525 | $525 | 3 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 274 EA | $400 | $351 | 2 |
| Feb 25, 2025 | Bank Stabilization on SR 37 over Oakohay Creek (Bridge No. 4.3)Covington | 4 EA | $1,000 | $1,000 | 8 |
| Jan 28, 2025 | Bridge Replacement on SR 14 over Hashuqua Creek (Bridge No. 156.5)Noxubee | 20 EA | $375 | $375 | 5 |
| Jan 28, 2025 | Drainage Improvements on US 61 near BlakelyWarren | 8 EA | $888 | – | 1 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 13 EA | $412 | $600 | 3 |
| Nov 26, 2024 | Intersection Improvements on US 49 at SR 35Covington | 7 EA | $431 | $425 | 3 |
| Nov 7, 2024 | Bridge Replacement on SR 12 over the Sunflower River (Bridge No. 23.9)Humphreys, Washington | 46 EA | $410 | $473 | 4 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.