The low bidder priced impact attenuator, 45 mph at a median $5,000 per each over the last 12 months (7 contracts), down 39% from the year before and down 6% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 2 EA | $4,307 | – | 1 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 9 EA | $6,250 | $5,581 | 6 |
| Sep 22, 2026 | Bridge Repair on SR 348 over Kings Creek (Bridge No. 0.9)Union | 2 EA | $5,300 | $5,300 | 6 |
| Jul 28, 2026 | Intersection Improvements on MS 42 from I-59 to Sunrise RoadForrest | 18 EA | $6,915 | $6,709 | 3 |
| Jul 28, 2026 | Bridge Repair on MS 4 over Tenn-Tom Waterway (Bridge No. 158.5)Tishomingo | 2 EA | $5,000 | $5,925 | 8 |
| Nov 25, 2025 | Bridge Repair on SR 3 over Short Creek, Bridge No. 32.7Yazoo | 2 EA | $4,500 | $4,920 | 5 |
| Nov 20, 2025 | Emergency Slide Repair on MS 478 approximately 0.90 miles SE of Shivers RoadSimpson | 2 EA | $4,000 | $4,221 | 5 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 3 EA | $6,570 | $7,000 | 3 |
| Apr 1, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 1 EA | $8,250 | $8,978 | 2 |
| Feb 4, 2025 | Roundabout Construction on SR 15 at SR 16 & Bridge Replacements on Weyerhaeuser Street oveNeshoba | 1 EA | $11,470 | – | 1 |
| Oct 22, 2024 | Bridge Replacements on SR 346 over Mud Creek & Ditch (Bridge Nos. 3.6 & 3.8)Pontotoc | 1 EA | $5,500 | $7,625 | 4 |
| Oct 10, 2024 | Emergency Slide Repair on US 80 in ForestScott | 2 EA | $6,044 | $5,522 | 2 |
| Jan 24, 2024 | Safety Improvements on approximatelyLowndes | 8 EA | $4,000 | $9,850 | 3 |
| Nov 28, 2023 | Bridge Repair on SRMadison | 2 EA | $4,550 | $4,550 | 3 |
| Nov 2, 2023 | Bridge Replacements & Bank Stabilization on US 98 at the Pearl River (Bridge Nos. 118.5A &Marion | 1 EA | $15,000 | $12,500 | 2 |
| Feb 28, 2023 | Construction project, Attala CountyAttala | 2 EA | $4,500 | – | 5 |
| Nov 23, 2021 | Construction project, Lee CountyLee | 2 EA | $5,350 | $5,350 | 5 |
| Oct 27, 2020 | Construction project, Neshoba CountyNeshoba | 4 EA | $4,750 | $4,885 | 3 |
| Feb 25, 2020 | Grade, Drain, Bridge, & Pave 4-Lane approximately 9 miles of APD Corridor "V" between FairItawamba | 2 EA | $5,847 | $5,847 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.