The low bidder priced 12.5-mm, ht, asphalt pavement at a median $190 per ton over the last 12 months (10 contracts), up 11% from the year before and up 77% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Mill & Overlay approximately 7.4 miles of I-55 from the Carroll County Line to 0.5 miles sGrenada, Carroll, Montgomery | 302 TON | $261 | – | 1 |
| Oct 27, 2026 | Construction project, Madison CountyMadison | 29K TON | $148 | $158 | 3 |
| Oct 27, 2026 | Mill & Overlay approximately 5.8 miles of I-20 from the Mississippi River Bridge to 0.65 mWarren | 3.6K TON | $199 | $205 | 3 |
| Sep 29, 2026 | Add 2 Lanes on SR 25 from Grants Ferry to SR 471, Ramp Improvements & Roundabouts on MS 47Rankin | 23K TON | $147 | $158 | 6 |
| Sep 22, 2026 | Restricted crossing U-Turn (RCUT) on US 82 at Sturgis-Maben Road & Mill & Overlay approximOktibbeha | 6.0K TON | $146 | – | 4 |
| Jul 28, 2026 | Traffic Signal and Interchange Modifications on US 45 & US 278Lee | 75 TON | $278 | $251 | 5 |
| Jun 23, 2026 | Overlay and OGFC Lift from east of the Shorecrest Road Overpass to approximately 0.9 mile Harrison | 14 TON | $750 | $725 | 2 |
| May 27, 2026 | Intersection Improvements on US 45 from Misso Road to Magnolia Drive, and Mill & Overlay aNoxubee | 14K TON | $181 | $173 | 2 |
| Nov 25, 2025 | Safety Improvements on US 84 at MS 184 & at MS 588 in CollinsCovington | 1.3K TON | $128 | $143 | 4 |
| Oct 28, 2025 | Mill, Level & Overlay approximately 4 miles of US 49 from US 11 to beginning of divided seForrest | 20 TON | $285 | $247 | 2 |
| Sep 4, 2025 | Roundabout on I-55 at the Brookway Boulevard InterchangeLincoln | 874 TON | $186 | $189 | 3 |
| Jun 24, 2025 | Directional Median Installation on US 49 at Siloam Road and a Traffic Signal at SR 149Simpson | 360 TON | $171 | $173 | 2 |
| Mar 25, 2025 | Mill & Overlay approximately 7 miles of I-20 from 5.1 miles east of SR 15 to 2.3 miles easNewton | 731 TON | $163 | – | 1 |
| Feb 25, 2025 | Safety Improvements on US 49 from the crossover past US 49 at the SR 13 interchange to 100Simpson | 1.8K TON | $162 | $170 | 5 |
| Feb 25, 2025 | Mill & Overlay approximately 14 miles of US 72 from the Tippah County Line to SR 2Alcorn | 27K TON | $130 | $136 | 3 |
| Dec 5, 2024 | Interchange Reconstruction on I-20 at FlowersWarren | 1.9K TON | $194 | $194 | 3 |
| Nov 26, 2024 | Installation of Intelligent Transportation Systems on I-59 from 1.5 miles south of I-20, ILauderdale | 120 TON | $372 | $588 | 4 |
| Oct 22, 2024 | Bridge Repair on I-20 over the Big Black River & Reliefs (Bridge Nos. 17.3A, 17.3B, 17.7A,Hinds, Warren | 664 TON | $191 | $230 | 2 |
| Sep 25, 2024 | Overlay approximatelyKemper | 5.7K TON | $181 | $181 | 3 |
| Jul 30, 2024 | Pavement Restoration on approximately 11 miles of US 49 from 0.8 miles north of Old HighwaYazoo | 43K TON | $97.00 | $118 | 3 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.