The low bidder priced bridge concrete, class bdx at a median $1,331 per cubic yard over the last 12 months (8 contracts), down 8% from the year before and up 40% since 2020.
| Let | Contract | Quantity | Winning price | All bidders' median | Bidders |
|---|---|---|---|---|---|
| Oct 27, 2026 | Construction project, Madison CountyMadison | 1.7K CY | $1,701 | $1,701 | 3 |
| Oct 27, 2026 | Bridge Replacement on SR 28 between the Copiah County Line & Pinola (Bridge Nos. 72.7 & 73Simpson | 1.3K CY | $1,298 | – | 1 |
| Sep 1, 2026 | Bridge Replacement on US 51 over unnamed Streams (Bridge Nos. 11.7 & 12.1) & between MagnoPike | 222 CY | $1,364 | $1,380 | 3 |
| Sep 1, 2026 | Bridge Replacements on SR 32 between Webb & Charleston (Bridge Nos. 45.6, 46.2 & 47.0)Tallahatchie | 1.1K CY | $1,600 | $1,600 | 6 |
| Aug 25, 2026 | SR 145 Bridge Replacement (Bridge No. 210.8), Known as Federal Aid Project No. STBG-0053-0Lee | 106 CY | $1,250 | $1,428 | 8 |
| Jul 28, 2026 | Bridge Repair on SR 16/SR 149 over SR 3 & Yazoo River (Bridge No. 203.3)Yazoo | 404 CY | $1,400 | $1,500 | 5 |
| May 27, 2026 | Bridge Replacement on SR 427 (Bridge No. 4.4) between SR 488 & SR 16Leake | 255 CY | $1,245 | $1,475 | 8 |
| Nov 25, 2025 | Bridge Replacement on SR 481 between SR 902 & SR 35 (Bridge Nos. 2.1 & 2.3)Smith | 184 CY | $1,260 | $1,497 | 7 |
| Sep 23, 2025 | Bridge Replacement on SR 704 (Bridge No. 162.5)Benton | 129 CY | $1,450 | $1,475 | 4 |
| Sep 23, 2025 | Grade, Drain, Bridge & Pave 4 Lanes on SR 7 from CR 370 to 0.4 miles south of SR 6, known Lafayette | 5.6K CY | $1,445 | $1,675 | 3 |
| Jun 26, 2025 | Bridge Replacements on US 80 between Chunky & Meehan (Bridge Nos. 123.1, 123.3, 123.5 & 12Lauderdale, Madison, Newton | 5.7K CY | $1,875 | $2,055 | 3 |
| Mar 4, 2025 | Grade Bridge, Pave 2-Lane on SR 19 from 0.25 miles South of SR 492 to Tucker DriveNeshoba | 2.2K CY | $1,500 | $1,630 | 2 |
| Jan 28, 2025 | Bridge Replacement on SR 14 over Hashuqua Creek (Bridge No. 156.5)Noxubee | 601 CY | $1,350 | $1,300 | 5 |
| Nov 26, 2024 | Bridge Repairs on SR 310 over Greasy Creek (Bridge No. 45.6)Lafayette | 166 CY | $975 | $2,250 | 6 |
| Oct 22, 2024 | Bridge Replacements on SR 346 over Mud Creek & Ditch (Bridge Nos. 3.6 & 3.8)Pontotoc | 336 CY | $1,200 | $1,284 | 4 |
| Oct 22, 2024 | Bridge Repair on I-20 over the Big Black River & Reliefs (Bridge Nos. 17.3A, 17.3B, 17.7A,Hinds, Warren | 1.1K CY | $2,000 | $1,755 | 2 |
| Jul 30, 2024 | Bridge Replacement on SRSunflower | 548 CY | $1,300 | $1,388 | 4 |
| Apr 23, 2024 | Grade, Drain, Pave on SR 2 from existing SR 15 to SRTippah | 542 CY | $1,500 | $1,375 | 2 |
| Apr 2, 2024 | Construction project, Madison CountyMadison | 1.2K CY | $1,175 | $1,400 | 7 |
| Jan 31, 2024 | Bridge Replacement on USJackson | 748 CY | $1,300 | $1,350 | 5 |
Source: MDOT bid tabulations, January 2020 through the October 27, 2026 letting. Compiled and checked by BidCrew. Only bids whose line items add up to the bid total (within 2%) are used.
BidCrew shows each competitor's history on every MDOT pay item, line by line, before the letting.